Blog module icon

Public Improvement Projects

Subscribe to this feed for public improvement project updates by the Transportation and Engineering Division.

Link to Public Improvement Projects webpage.

View All Posts

Jan 03

S. Alkire Street Improvements (S. Zang Court to W. Belleview Avenue) Littleton, CO 80127

Posted on January 3, 2022 at 8:52 AM by Lindsay Townsend

Project Location:
Improvements will be completed along the east side of S. Alkire Street from S. Zang Court to W. Belleview Avenue.

Link to see S. Alkire Street (S. Zang Court to W. Belleview Avenue) on a map

Project Scope:
S. Alkire Street roadway improvements will be constructed between S. Zang Court and W. Belleview Avenue. The project will include:

  • Widening the east side of the roadway to allow two 11-foot northbound travel lanes
  • Adding left turn lanes
  • Adding a four-foot bike lane on the east side of the roadway
  • Raised concrete medians
  • Curb and gutter, and eight-foot sidewalks on the east side of S. Alkire Street
  • Storm drainage improvements

 See FOR Construction Plans (PDF) (101.7 MB)

This project has been awarded to Hamon Infrastructure Inc. in the amount of $1,960,000.00.

Project Update (as of January 3, 2021): 
The general contractor, Hamon Infrastructure Inc. (Hamon) completed all major construction activities along S. Alkire Street. The final asphalt work is to be completed Spring 2022 by Jefferson County. Hamon continues to be on site with small crews resetting fences, performing general cleanup and other final construction activities.

There are times when S. Alkire Street will be reduced to one lane of travel in each direction through the project site. The speed limit is reduced to 25 mph with fines doubled in the construction zone.

If you have additional project questions or concerns, please call the project hotline at (303) 297-0340 or email Hamon Infrastructure Inc.