The original item was published from October 26, 2022 2:35 PM to September 6, 2023 9:16 AM
Project Location:
The project was located at the intersection of 44th Avenue and McIntyre Street in unincorporated Jefferson County.
Project Scope:
Construction crews replaced the existing span wire traffic signal system with mast arm traffic signals. They also repaired concrete, and completed final asphalt mill and overlay with striping.
The project was awarded to Goodland Construction in the amount of $913,215.75.
Project Update (August 2, 2023):
The project was finished July 19, 2023. Crews will perform minor cleanup and repair work at the intersection through the next month.
Thank you for your patience during this project.