Blog module icon

Public Improvement Projects

Subscribe to this feed for public improvement project updates by the Transportation and Engineering Division.

Link to Public Improvement Projects webpage.

View All Posts

Sep 06

W. 32nd Avenue Roadway Widening (Coors to McIntyre Street), Golden, CO 80401

Posted on September 6, 2022 at 8:11 AM by Lindsay Townsend

Project Background:

The section of West 32nd Avenue from Coors to McIntyre Street is classified as a Major Collector Road with high truck traffic. It is also identified on the Jefferson County Bike Plan (PDF) (56.9 MB) with proposed paved shoulders. The current configuration does not meet county standards for a roadway with this classification level. Jefferson County seeks to widen West 32nd Avenue to meet current county standards and improve safety along the roadway.

Jefferson County is working with Lee Stewart and Eskin Ditch to realign portions of the ditch facility and limit impacts to future maintenance of the roadway and ditch.

View this project on the Jeffco Roadway Project dashboard (an interactive mapping application). Under the Capital Improvement Project list at the right-hand side of the dashboard, scroll to and click "32nd Ave Shoulder Widening".

Project Scope:

The project includes modification of West 32nd Avenue to a standard roadway template with the installation of four-foot paved shoulders, mill and overlay of the roadway surface, and restriping of the travel lanes. Construction will also involve necessary work for the paved shoulder widening which includes clearing and grubbing, removal of necessary trees along the north side of the roadway for grading activities, realignment of portions of the existing irrigation ditch, and installation of retaining walls and guardrail.

The project will be divided into two construction phases. Phase 1 project limits are to the east of the first Coors facility access driveway and west of the intersection at West 32nd Avenue and McIntyre Street. 

Link to W. 32nd Avenue phasing limits and typical sections.See Project Limits and Typical Sections (PDF)

Project Schedule:

Phase 1 construction including shoulder widening and paving began the week of August 29. The construction work will likely last two to four weeks. Phase 2 site preparation and grading work will occur starting in late October / early November 2022 and likely last 8 to 12 weeks (weather depending). Phase 2 roadway work will occur in the summer of 2023.

Project Impact on Traffic:

During Phase 1 construction, the roadway will be reduced to a single lane of traffic controlled by flaggers. Please expect delays.