Project Background:
In July 2021, the existing corrugated metal pipe failed during a heavy local rain event. The county installed plastic pipes and steel plates as a temporary measure to allow traffic until the permanent design could be completed.
Project Scope:
The existing corrugated metal pipe was replaced with an elliptical concrete pipe. The project also included installing riprap areas on the upstream and downstream sides of the culvert for erosion protection.
Project Schedule:
This project is complete.