W. Quincy Avenue Phase 2 Roadway (S. Beech Way to S. Swadley Court), Morrison, CO 80465

Posted on December 1, 2023 at 10:17 AM by Lindsay Townsend

Bar shows construction of Quincy Avenue Phase 2 as 50 percent complete. Completion August 2023.

Link to see Quincy Avenue Phase II roadway layout.

Jefferson County's consultant completed the final design of West Quincy Avenue Phase 2 Roadway Reconstruction from South Beech Way to South Swadley Court. This will be second phase of the Quincy Avenue Corridor Improvements to widen the road to a major collector roadway standard. The project was bid out and awarded to Concrete Express Inc. (CEI) for $6,673,823.26.

View this project on the Jeffco Roadway Project dashboard (an interactive mapping application). Under the Capital Improvement Project list at the right-hand side of the dashboard, scroll to and click "Quincy Phase 2 - Beech Way to Swadley Ct".

Utilities:

Utility agencies and their contractors completed their respective underground utility line relocations in advance of the roadway reconstruction.

Schedule:

There may be work continuing on West Quincy Avenue periodically as the contractor finishes miscellaneous punch list items to complete the project. Please drive slowly and use caution around the construction equipment and crews.

For Questions:

Please call CEI's project information hotline at 720-593-8871 or send an email..

Thank you for your interest in this project!