Public Improvement Projects

Subscribe to this feed for public improvement project updates by the Transportation and Engineering Division.

Link to Public Improvement Projects webpage.

View All Posts

May 12

S. Kipling Parkway Roadway Improvement Project, Littleton, CO 80127

Posted on May 12, 2022 at 9:03 AM by Lindsay Townsend

Project Overview:

Link to larger image of Kipling Roadway Improvement Project Site Map.Improvements will be completed at the intersection of S. Kipling Parkway and W. Bowles Avenue from north of W. Fair Avenue to north of S. Jellison Circle. 

Project Scope:

This project will improve the intersection of S. Kipling Parkway and W. Bowles Avenue, and do the following: 

  • Replace existing span wire traffic signals with mast arm traffic signals and four new traffic signal poles. 
  • Remove and reconstruct portions of existing concrete medians, curb ramps, curb, gutter, and sidewalk. 
  • Construct a third northbound through lane on S. Kipling Parkway. 
  • Construct drainage improvements. 
  • Patch asphalt in select areas and complete the intersection with a nominal two-inch mill and overlay.

This project has been awarded to SEMA Construction, Inc. in the amount of $2,387,458.90. 

Project Documents:

Project Update (as of May 11, 2022):

The general contractor, SEMA Construction, Inc. (SEMA) is expected to begin work on the S. Kipling Parkway Improvement Project the week of May 16. The contractor will mobilize to the site and set up erosion and traffic control devices, then proceed with modifications of the center medians on S. Kipling Parkway near W. Bowles Avenue. 

Construction is anticipated to continue through October 2022. There will be times when the number of traveled lanes on S. Kipling Parkway will be reduced through the project site. The speed limit will be reduced with fines doubled in the construction zone. 

For Questions:

If you have additional project questions or concerns, please call the project hotline at 720-615-0020 or send an email.