Blog module icon

Public Improvement Projects

Subscribe to this feed for public improvement project updates by the Transportation and Engineering Division.

Link to Public Improvement Projects webpage.

View All Posts

Mar 01

JC-73 Roadway Improvements (Buffalo Park Road to Plettner Lane) Evergreen, CO 80439

Posted on March 1, 2023 at 4:19 PM by Lindsay Townsend

Project Overview:

Jefferson County is planning improvements to JC-73 between Buffalo Park Road and Plettner Lane beginning mid-2023. Benefits to the public will include:

  • Safety enhancements to the intersection of Buffalo Park Road and JC-73;
  • Left Turn Lanes;
  • A Concrete Pedestrian Trail;
  • Drainage and Flood Controls; and
  • Bridge Replacements at Cub Creek.

The project will be funded in part with a grant of $8.75 million from the Federal Highway Administration (FHWA). Jefferson County's share is estimated to be $2.19 million.

Link to larger cross section of JC-73 looking north towards downtown Evergreen.  Link to larger image of JC-73 Layout Exhibit. View this project on the Jeffco Roadway Project dashboard (an interactive mapping application). Under the Capital Improvement Project list at the right-hand side of the dashboard, scroll to and click "CR73 Roadway Improvements". 

Project Schedule:

Preliminary design and public outreach efforts were conducted throughout 2021. Final design is nearly complete and currently undergoing state and federal agency review. Additional public presentations of the final design will be scheduled for March 2023 for both virtual and public venues. Additional information and links to plans will be provided in the next month.

After final plan review, the project will be advertised for construction bids. Construction is expected to begin in the summer 2023 and continue through 2024. Construction is planned to progress from Plettner Lane to Buffalo Park Road in several phases. Traffic impacts should be expected throughout the construction project as JC-73 is reduced to a single lane during daytime and evening work activities.

Utility Relocations and Site Preparation:

Utilities are currently being relocated in advance of roadway construction. Gas main relocation and service connections in JC-73 have been ongoing since November 2022. Gas work is expected to be completed by the end of January 2023. Electric line relocations and improvements have also been started in areas east of JC-73 near Evergreen Library. Additional electric work in JC-73 will occur later this spring.

Site preparation will also commence in February as structure demolition across from Evergreen Fire Department occurs.

UTILIY RELOCATION UPDATE

Xcel crews have been taking advantage of warm weather and working during the evenings this week to complete new gas service relocations.

Saturday morning of February 4, crews will have to patch asphalt to avoid road damages. This work is critical in advance of cold temperatures and a snowstorm forecast for early next week.

Then on Monday evenings, crews expect to finish the last gas line work. This will be followed up Thursday, February 9, with final asphalt patching during the daytime. All work is weather dependent.

Daytime work will have Uniformed Traffic Control at the intersection of JC-73 and Buffalo Park Road.

Thank you for your continued patience during this phase of utility work.

Link to larger image of the JC-73 and Buffalo Park Road intersection.

Stakeholder Engagement Process:

Public involvement and feedback provided in 2021 were incorporated in the final design. Jefferson County will continue to develop a public information pan to implement during construction. Efforts are currently underway to identify and incorporate the needs of Evergreen Schools, Evergreen Fire Department, Jefferson County Sheriff's Office, Evergreen Parks and Recreation, the Evergreen Chamber of Commerce, and area businesses. The information plan will focus on ways to: (1) Reduce traffic congestion, (2) Communicate planned work events, and (3) accommodate fire and emergency response.

Evergreen Lake North Trail Project:

The county is coordinating with Evergreen Metro District and the Colorado Department of Transportation (CDOT) to mitigate the traffic impacts from construction of Evergreen Lake North Trail Project on JC-73 and CO-74. See Evergreen Park and Recreation District's project webpage for more information.

For Questions:

Your feedback is valuable in the decision-making process. For questions, please email Mike Vanatta.

Thank you for your interest in this project!